AS/NZS 1554: A Practitioner's Guide to Welding Steel Structures
Contact us for a quoteAS/NZS 1554 is the Australian and New Zealand standard series for welding steel structures. Part 1, AS/NZS 1554.1:2014 incorporating Amendments 1 and 2, covers general steel structures and is the part usually meant by ‘AS 1554’. Every weld under it needs a qualified procedure, a qualified welder, a qualified welding supervisor, and compliance with the rest of the standard (cl 1.7.2).
This guide follows a job from the drawing to the inspection report, with the clause for each point.
By Graham Fry, International Welding Engineer (IWE), Technoweld. Clause references checked against AS/NZS 1554.1:2014 incorporating Amendments 1 and 2.
Seven parts, and when Part 1 is the wrong one
Part 1 covers steel structures welded by MMAW, SAW, GMAW (pulsed included), GTAW, FCAW, electroslag and electrogas, in parent material with a specified minimum yield strength up to 500 MPa (cl 1.1). It doesn’t cover pressure vessels or pressure piping (cl 1.2). Those go to AS 1210, AS 4041 and AS/NZS 3992.
The other parts take over where Part 1 stops:
- AS/NZS 1554.2, stud welding.
- AS/NZS 1554.3, welding of reinforcing steel.
- AS/NZS 1554.4, high strength quenched and tempered steels.
- AS/NZS 1554.5, structures subject to high levels of fatigue loading. It adds weld category FP, for stress ranges above detail category 112 of AS 4100.
- AS/NZS 1554.6, stainless steels for structural purposes.
- AS/NZS 1554.7, sheet steel structures up to 4.8 mm thick.
Fatigue is where a specification can name the wrong part. Part 1 does cover dynamically loaded welds, cranes, hoists and bridges included, but only inside the stress range limits in cl 1.1. Above detail category 112, it’s Part 5. If a crane runway drawing names only Part 1, confirm the design stress range before anyone cuts steel.
Read the drawing before you price it
Appendix D is the most useful page in Part 1. It’s normative. It lists 25 matters of a contractual nature that “shall be resolved”, items (a) to (y), and recommends the principal (the client or their nominated representative) settles them with the fabricator before work starts.
A drawing that just says “weld to AS 1554” leaves almost all of them open. The ones that change the price:
- The weld category for each weld, item (a).
- Approval of welding procedures and the method of qualification, items (d) and (e).
- Qualifications of the welding supervisor and the welders, items (l) and (m).
- Type and extent of inspection and non-destructive examination (NDE, usually called NDT), item (t), and the NDE technique, item (u).
- Who corrects faulty welds, and who pays for the repair and the NDE that follows it, item (v).
- Whether a test report is required, item (w).
- On plate 20 mm and over, whether part of each multi-pass butt weld is tested for transverse cracks, item (y).
Get them answered in writing at quote stage. Any left open can become a variation, or an argument, at the first hold point.
GP or SP: the category belongs to the weld
Part 1 has two weld categories, GP (general purpose) and SP (structural purpose), defined in cl 1.6. Read the two lists side by side and statically loaded AS 4100 welds appear in both. Welds stressed above 50% of the AS 3990 permissible stress, and dynamically loaded welds within cl 1.1, point to SP. Non-structural welding points to GP. The standard doesn’t pick the category for you. The designer does, weld by weld, and Appendix D item (a) makes it a matter for resolution. A beam can carry SP butt welds in the flanges and GP fillets on its cleats.
The category drives the acceptance criteria. On a butt weld examined visually (Table 6.2.2), SP allows no cracks at all, while GP accepts crater cracks only, up to 6 mm cumulative in 1,000 mm of weld. Continuous undercut is limited to t/10 (1.5 mm maximum) for GP and t/20 (1 mm maximum) for SP. Undercut less than 0.5 mm deep is disregarded. The radiographic and ultrasonic acceptance levels in Table 6.2.1 are written for Category SP only, and imperfections that originate in the parent metal aren’t a reason to reject the weld (cl 6.2.2).
An SP weld that misses SP isn’t automatically scrap. It may be accepted as GP, provided the design standard is still satisfied and the principal agrees (cl 1.6, Note).
Six ways to qualify a welding procedure
Clause 4.2 gives six ways to qualify a procedure: (a) prequalified to cl 4.3, (b) documented prior experience, (c) a production test piece, (d) a special test piece, (e) destructive testing of a prototype, and (f) another fabricator’s procedure under cl 4.4. Route (a) is the usual starting point for structural work, and prequalified still needs evidence. Clause 4.3.1 sets five conditions, and the last is documentary evidence of a satisfactory macro test (an etched cross-section of the weld): the macro, or a sketch or photograph of it, showing the position, the run sequence, the minimum leg length, the throat thickness and the scale. No macro, no prequalified procedure.
Two other details matter. Self-shielded flux-cored wire mixed with any other consumable type is never prequalified and has to be qualified by test (cl 4.3.2). And a complete penetration butt weld welded from both sides on a prequalified preparation has to be backgouged to sound metal before the second side, unless a macro etch shows complete fusion without it (cl 4.5.2).
Clause 4.1.1 puts the work on the fabricator: establish the procedure, hold the procedure qualification record (PQR), develop the welding procedure specification (WPS) from it within the essential variables of cl 4.11, and give it to the welder. Where the principal’s representative approves the procedure, that person needs at least a welding supervisor’s qualification under cl 4.12.1 or an inspector’s under cl 7.2.
Technoweld writes and reviews AS/NZS 1554 WPSs and PQRs, and witnesses procedure tests. See welding procedures.
Working out preheat to cl 5.3.4
Clause 5.3.4 sets out how to determine minimum preheat. In short:
- Get the weldability group for the steel from Table 5.3.4(A), or calculate the carbon equivalent from the ladle analysis, add 0.01 and use Table 5.3.4(B).
- Work out the combined thickness of the joint, Figure 5.3.4(A).
- Read off the joint weldability index, A to L.
- Read the arc energy and minimum preheat combination from Figure 5.3.4(B) for hydrogen controlled processes, or 5.3.4(C) for the rest.
Arc energy is Q = 60EI / 1000V, in kJ/mm, with E the arc voltage, I the current and V the travel speed in mm/min. For pulsed welding, use the average voltage and current. That’s why the WPS needs real arc energy figures. The preheat on it is only right for the arc energy it was worked out at.
If you want a preheat that wasn’t determined by this method, the procedure has to be qualified to Section 4. The standard also says plainly that the method addresses heat affected zone cold cracking, not weld metal cold cracking.
Site conditions sit in cl 5.4. No gas shielded welding in wind above 10 km/h unless the area is screened below that, or a procedure is qualified for it. No welding or thermal cutting when the metal is colder than 0°C, unless the procedure is qualified for it. Tack welds (cl 5.5) carry the same quality and preheat requirements as the final weld, need cascaded ends if multi-run, and must be at least the lesser of 40 mm and four times the thickness of the thicker part.
Welders: two ways in, and when the qualification lapses
The fabricator gives the principal evidence that each welder is qualified and keeps a record of every welder and test for the inspector (cl 4.12.2.1).
A welder qualified to AS 1796, AS/NZS 2980, AS/NZS 3992 or ISO 9606-1 is deemed qualified, provided the qualification covers joints and positions as close as practicable to the work (cl 4.12.2.2). Otherwise the welder welds a test piece for each procedure on the job, at least 300 mm long, examined visually and by macro against Table 6.2.2 (cl 4.12.2.3).
A welder’s qualification stays valid while the employer’s records show reasonable continuity on the process and continued sound welds verified by NDE. Reapproval is needed after six months or more off the process, when there’s a specific reason to question the welder’s ability, and when the welder changes employer, unless the qualification is to AS/NZS 2980 or ISO 9606-1 (cl 4.12.2.4). That’s worth knowing when choosing which qualification to hold. The test itself is covered on our welder qualification testing page.
Technoweld runs AS/NZS 1554, AS/NZS 2980 and ISO 9606-1 welder tests under NATA accreditation. See welder qualification.
Welding supervisor qualifications under cl 4.12.1
All welding is done under a welding supervisor employed by or contracted to the fabricator (cl 4.12.1). The supervisor makes sure the welding follows the drawings and the WPS, makes the WPS available at the workplace, runs checks before, during and after welding, and takes remedial action when imperfections turn up.
The minimum is three years’ experience in the fabrication of welded structures, plus one of: a welding supervisor’s certificate to AS 2214, AS 1796 Certificate No. 10 or the NZIW equivalent; an IIW diploma at IWS, IWT or IWE level; an NZIW certificate in welding engineering; a postgraduate qualification in welding engineering; or other qualifications and experience acceptable to the principal that conform to ISO 14731.
The supervisor may test welders under their supervision, and issue and prolong the welders’ qualification certificates. Others can help with surveillance, but the responsibility stays with the supervisor (Note 2). ‘Supervision’ in cl 4.12.1 means checks before, during and after welding. It’s an active role, not a sign-off.
Inspection: what the standard requires and what it leaves to the drawing
Section 7 covers inspection by the inspecting authority or the principal. The inspector gets access to all relevant phases of the work, reasonable notice before welding starts, and the chance to witness procedure and welder tests (cl 7.1).
Clause 7.2 accepts an IIW Welding Inspector diploma, a WTIA welding inspector certificate or CBIP-NZ welding inspector at the appropriate level, an AS 2214 certificate, or other qualifications acceptable to the principal. Note 3 says the inspector should not be involved in supervising the fabrication. Keeping the two roles separate is what gives the inspection its independence.
Visual inspection does most of the work. The inspector checks set-up before and during welding and checks that no weld on the drawings is missing, and cl 7.3 says all welds receive a full visual inspection in accordance with Section 6, carried out to AS 3978. Table 7.4, which is guidance, treats visual as two activities: visual scanning of every weld for missing welds and gross defects, and detailed visual examination against Table 6.2.2, suggested at 5 to 25% of GP welds and 10 to 50% of SP welds. The two sit awkwardly together, so state the extent of detailed visual examination in the inspection and test plan (ITP) before the inspector turns up.
Beyond visual, Part 1 sets no default amount of NDE. Where NDE is specified, the drawings or other documents have to state the methods and the extent (cl 7.4). Table 7.4 suggests up to 10% radiography or ultrasonics and up to 10% magnetic particle or penetrant for SP, and no volumetric testing for GP. Its notes suggest testing the first major component or 5% of welds in full, then easing off as compliance is shown. NDT personnel certified to AS 3998 or by CBIP-NZ are deemed qualified.
Technoweld is a NATA accredited Type A inspection body (No. 19221) with AS/NZS 1554.1 to .7 in scope. See welding inspection, and build the hold points into an ITP before the first weld.
Where the quality system fits
Clause 1.7.1 requires welding to be managed under a suitable quality management system, which should generally comply with the AS/NZS ISO 3834 series, particularly on large, complex or critical structures. AS/NZS 1554.1 says what each weld needs. ISO 3834 is the framework a shop uses to show it does that consistently. See ISO 3834.
AS/NZS 1554 questions clients ask
Is AS 1554 the same as AS/NZS 1554.1?
Usually. Drawings still say AS 1554 and mean Part 1, but ask, because fatigue, stainless, sheet steel and quenched and tempered work sit in other parts. Part 1 is currently the 2014 edition incorporating Amendment 1 (2015) and Amendment 2 (2017).
Does a prequalified procedure need any testing?
Not a full qualification test, but it needs documentary evidence of a satisfactory macro (cl 4.3.1(e)).
Can we use a procedure qualified to another standard, or by another fabricator?
Yes, within limits. A procedure qualified to another application standard, such as AS/NZS 3992, counts as prior experience if the parent material complies with Appendix B, the consumables with cl 2.3 and the imperfections with cl 6.2 (cl 4.2(b)). Another fabricator’s procedure is valid if the original qualification is fully documented, your shop proves it with welder tests or a macro, both fabricators and the principal accept it, and the WPS names both (cl 4.4).
Does an AS 1796, AS/NZS 2980 or ISO 9606-1 ticket cover AS/NZS 1554 work?
Yes, if it covers joints and positions as close as practicable to the work (cl 4.12.2.2). Only AS/NZS 2980 and ISO 9606-1 survive a change of employer (cl 4.12.2.4).
How much NDT does AS/NZS 1554.1 require?
Visual inspection of all welds (cl 7.3). Anything more has to be specified, with method and extent on the drawings or other documents (cl 7.4). The Table 7.4 ranges are suggestions.
Can our welding supervisor also be our inspector?
The standard recommends against it. Clause 7.2, Note 3, says the inspector should not be involved in supervising the welded fabrication.
Send us the drawing
Send the drawing and specification. We’ll list what Appendix D leaves open, write or review the WPSs and qualify the welders. Where you need independent inspection under our NATA accreditation, we’ll confirm first that it doesn’t conflict with other work we’re doing on the same job.