Services

Productivity improvement

The time is in the procedure. We take it out.

Fewer runs. Less weld metal. Less time with the arc off. We run the trials, change the procedures and train your welders on the job.

  • NATA Accreditation No. 19221
  • ISO/IEC 17020 Type A inspection body
  • ISO 9001:2015 certified
  • International Welding Engineer sign-off
  • Offices in SA and NSW. Working nationally and overseas.

What we do on your floor

  • Trials. We weld the alternatives and time them.
  • Procedure changes. The procedure that wins is written up and put to work.
  • On-the-job training. Our people show your team, roll their sleeves up and train them on the job.

Assessment and plan by Graham Fry

The assessment of where the time is going, and the plan to take it out, are prepared by Graham Fry. Technoweld carries the plan out: the trials, the procedure changes and the on-the-job training.

grahamfry.com.au

From our job records

Three examples of what changing the procedure did to the job.

01Stainless pipe butt

400NB Schedule 10 pipe butt, 316 stainless

We took this weld from 5 hours 19 minutes to 5.5 minutes. We changed the process, dialled in an advanced welding machine and took the joint from positional welding to rotated. The back purge went from 15 litres a minute for the whole 5 hours 19 to 5 litres a minute for 5.5 minutes.

58 times faster

5 h 19 min down to 5.5 min per weld, floor-to-floor

99.4% less purge gas

4,785 litres down to 27.5

Purge volume is flow rate multiplied by weld time: 15 L/min for 319 minutes, 5 L/min for 5.5 minutes. Both times are floor-to-floor.

02Plate butt weld

18 mm butt weld, time per metre

The existing procedure took eight runs: four GTAW, then four GMAW. We trialled two replacements. GTAW at 400 amps with FCAW fill takes five runs. Metal-cored wire takes three.

6.2 times faster

GTAW with FCAW fill, 2 h 33 min down to 24 min per metre

15.8 times faster

Metal-cored wire, 2 h 33 min down to under 10 min per metre

Time per metre is arc-on time from the recorded travel speeds, plus an allowance for stops and starts: arc on for 50% of the time with the existing procedure, 80% for GTAW with FCAW, 90% for metal-cored. The trial plate was 16 mm, so trial times are scaled up to the 18 mm joint by weld area, 98.15 against 84.3 mm². Arc-on time alone is 76.3, 19.6 and 8.7 minutes.

03Workshop audit

One day on a fabricator’s floor, 13 recommendations

A walk through four bays of pipe and structural work, with no document review. Three of the findings, with the numbers behind them.

78% more weld metal than the drawing asked for

Fillets laid at 8 mm where 6 mm was called for. That is 251 g a metre against 141 g, and 5.97 m an hour against 10.63.

29 to 38% less weld metal in a pipe butt

Calculated for a tighter butt preparation on 50NB, 80NB and 100NB Schedule 40 pipe.

41 to 11 minutes per pipe butt

150NB Schedule 80 on a rotator, from an earlier Technoweld job: a high-amp GTAW root in place of an STT root.

The first two are findings and calculations from the audit, before any change was made. The third is a measured result from another job, quoted in the audit report.

Figures from Technoweld job records and reports. Clients are not named.