By Graham Fry, International Welding Engineer
Too many ITPs are written to win the job or satisfy the client, not to run it.
They turn up in the tender. Twelve pages, a nice logo, every activity listed, and the acceptance criteria column says “as per spec” all the way down. Then the job starts, the ITP goes in a folder, and nobody opens it again until the MDR is due.
That’s not an inspection and test plan. That’s window dressing. The purpose of the ITP is to summarise the project quality obligation sequentially to ensure things do not get missed.
In Paperwork Is Not Proof I set out eight checks an asset owner can run before the first arc. Getting the ITP before fabrication starts was number two, and it’s the one that is worth getting right. It’s the only document that tells everyone, in advance, what gets checked, against what, by whom, and where the job stops. It is the workshop instruction developed by the QA manager to communicate what is required.
So here’s what a welding ITP in construction should contain, what the standards ask for, a sample you can read on this page, and two free templates. They can take many forms, this is one.
What an inspection and test plan is (ITP vs ITC)
An inspection and test plan is a plan. It’s written before the work starts and lists every inspection and test activity in the order the work happens.
An inspection and test checklist (ITC) is narrower. It’s the sheet someone fills in at one activity, say a fit up check on a single joint or task, they can also be used when a batch of similar components are getting made and the ITC is done for each part.
The ITP points to the ITCs. It doesn’t replace them. When an ITP tries to be both, it ends up as a fifty page spreadsheet nobody can use on the floor, and only gets signed at the end and typically never leaves the office.
What AS/NZS 5131, 1554.1 and ISO 3834 require in a welding ITP
AS/NZS 5131 Section 13 covers inspection and testing for structural steelwork, and Clause 13.6 deals with welding. Clause 13.6.1.2 lists the welding inspection items, (i) to (xxviii). Austroads ATS 5410-23 and Transport for NSW both ask for an ITP covering all of them for CC2 and above.
The construction category drives the extent. If the specification is silent, 5131 defaults to CC2. Steel Construction New Zealand reads 5131 as requiring documented ITPs from CC2 up. Put those two together and most structural jobs end up needing a documented ITP. Check your project specification.
AS/NZS 1554.1 Section 7 covers who can inspect and how: inspector qualifications, visual inspection and non destructive examination. The acceptance criteria themselves sit in Section 6, by weld category, SP or GP.
AS/NZS ISO 3834.2 Clause 14 splits inspection into before, during and after welding. That’s the most useful way to lay an ITP out, because it follows the job.
None of these standards hands you a finished ITP. They tell you what has to be covered. Turning that into a plan for your job is the fabricator’s work, and checking / approving it is the owner’s.
Hold, witness and review points
Get these three straight, because most arguments start here.
A hold point stops the job. Transport for NSW’s quality specification, Q6, defines it as “a point beyond which a work process must not proceed without the Principal’s written authorisation”. No release, no next step.
A witness point is a notice. You’re told in advance, you can attend, but if you don’t turn up, work goes ahead.
A review point is a document check. The procedure, the certificate or the report gets reviewed, usually without anyone attending.
Two things make a hold point work. A notice period written into the ITP, so the person releasing it can actually get there. And a named person with the authority to release it. A hold point with no notice period and no name is just a box.

How road agencies specify welding ITPs (TfNSW, TMR, SA DIT)
Even if you never build a bridge, the road agency specifications are worth a read. They’re public examples of welding ITP requirements in Australia, and they’re free.
Transport for NSW’s steel fabrication specification, TS 01744 (revision 1.0, December 2024), carries fifteen hold points and seven witness points. Documents are due fifteen working days before fabrication starts, and the welding plan, WPS and PQR approval and any crack repair are all hold points.
Queensland’s MRTS78 won’t let welding start until the WPS and PQR are approved. It holds before coating for a visual scan, holds on the NDT report review, and requires an approved weld map that records the WPS, the welder ID and the supervisor’s sign off for every joint.
Closer to home, SA’s Department for Infrastructure and Transport specification ST-SS-S1 (September 2024) wants an ITP covering the AS/NZS 5131 items, an independent inspector, and a supervisor and inspector who are not the same person. Results are recorded within five business days, not at the end of the job.
If your CC3 ITP has fewer hold points than a road agency uses, check each one has a reason, and that nothing’s missing. More isn’t better. Every hold point costs time and money on both sides. The right ones are.
Scaling the ITP to construction category
My rule of thumb, which is not a quote from the standard.
CC1. Mostly review points and visual inspection. WPS and welder qualifications reviewed, 100% visual, dimensions checked, records kept.
CC2. Add hold points on WPS approval, first off fit up and the NDT results, with NDT to the extent the category requires, hold before coating.
CC3 and CC4. Independent inspection at the hold points, NDE extent from Table 13.6.2.2(A) of AS/NZS 5131 (for CC4 the client specification sets it), full traceability, and a weld map with a WPS and welder against every joint.
The columns every ITP template needs
Every line in the ITP answers the same questions. If a column is blank, the line isn’t finished.
- Item number, in the order the work happens.
- Activity, described so the person on the floor knows exactly what is being checked.
- Reference, the standard, clause, drawing or procedure that governs it.
- Acceptance criteria, the actual criteria. A number, a tolerance, a weld category. Not “as per spec”.
- Method and extent, how it’s checked and how much of it.
- Frequency or lot, when the check happens and what it releases.
- Inspection point, hold, witness or review, with the notice period.
- Responsibility, by role and organisation. Fabricator, client, independent inspector, NDT provider.
- Record, the ITC or IR that proves it was done.
- Sign off, name, signature and date, at the time, for each party.
Put a header block on top: project, package, construction category, governing specification, revision, and who approved it.
Here’s the difference one column makes.
| Line | Activity | Acceptance criteria | Extent | Point | Record |
|---|---|---|---|---|---|
| Weak | Visual inspection | As per spec | As required | ||
| Good | Visual inspection of completed welds | AS/NZS 1554.1 Section 6, SP limits | 100% of welds | H, 24 hours notice, client QA | Visual IR, signed and dated |
A sample welding ITP, structural steel, CC3
This is an extract, not a complete ITP. It shows how the lines read when the columns are filled in properly.
| # | Activity | Reference | Acceptance criteria | Extent | Point | By | Record |
|---|---|---|---|---|---|---|---|
| 1 | Construction category confirmed | Drawings, AS/NZS 5131 cl 4.1.2 and Appendix C | CC3 stated on drawings and specification | All drawings | R | Client engineer | Drawing register |
| 2 | WPS and PQR approval | AS/NZS 1554.1 Section 4 | Every joint covered for process, position, thickness and material | All WPS | H, 5 days | Client QA | Approved WPS register |
| 3 | Welder qualifications | AS/NZS 2980 or ISO 9606-1 | Range covers the joints, continuity current | All welders | R | Welding supervisor | Welder register |
| 4 | Material traceability | AS/NZS 5131, EN 10204 3.1 | Grade and heat on certificate match the plate | All main members | R | Fabricator QA | Certificate register |
| 5 | Fit up, first off | WPS, drawing | Root gap, bevel and alignment within WPS | First off per joint type | W, 24 h | Independent inspector | Fit up ITC |
| 6 | Preheat and interpass | WPS | Within WPS range, measured at the joint | Each joint where required | R | Welding supervisor | Welding record |
| 7 | Visual inspection | AS/NZS 1554.1 Section 6 | SP limits | 100% of welds | H, 24 h | Independent inspector | Visual IR |
| 8 | NDT | AS/NZS 5131 Table 13.6.2.2(A) | SP limits, AS/NZS 1554.1 Section 6 | Extent for CC3, after the Table 13.6.2.1 hold time | R | NDT provider, NATA accredited | NDT reports |
| 9 | Repairs | Repair WPS, AS/NZS 5131 cl 13.6.2.5 | Reinspected to the original level, sample extended | Each repair | H | Welding supervisor | NCR and repair IR |
| 10 | Dimensional | Drawing, AS/NZS 5131 Section 12 and Appendix F | Within tolerance | Each member | W | Fabricator QA | Dimensional IR |
| 11 | Surface preparation and coating | Coating specification | Blast grade and DFT range stated on the line | Each member | H before coating | Coating inspector | Coating IR |
| 12 | Final release | Contract | All IRs complete and signed | Each lot | H | Client | MDR |
Welding ITP line items: before, during and after welding
Laid out the ISO 3834 way, a welding ITP for structural steel usually runs something like this.

Before welding. Construction category confirmed. WPS and PQR reviewed and approved. Welder qualifications and continuity checked. Material certificates reviewed and heat numbers matched to the plate. Consumables and storage checked. Weld map issued. Fit up, root gap, bevel and cleanliness checked on first off joints. Tack welds and working conditions checked.
During welding. Preheat measured at the joint before the arc and maintained. Parameters checked against the WPS. Interpass temperature. Back gouging and root inspection where required. Welder ID marked against the joint.
After welding. Visual inspection, 100%, to the weld category. Dimensional check against the drawing, including distortion. NDT once the weld has cooled and after any delay the specification or WPS sets. PWHT where specified, before final NDT. Repairs re-tested by the same method, with the sample extended where defects were found. NCRs closed. Welds dressed to suit the surface preparation grade. Surface preparation and coating inspection. Final release and the MDR.
Your job will add or remove lines. The point is the order. If coating sits above NDT on your ITP, you’ve got a problem.

Coating cut back at the field weld. The ITP says when that weld gets inspected and coated.
Six ways ITPs fail on real jobs
1. Acceptance criteria that say “as per spec”. If the inspector has to go and find the number, the inspection didn’t happen properly.
2. One giant ITP for everything. Split it by package or by stage so the people using it can find their line.
3. Activities out of sequence. Inspection points that sit after the activity they were meant to hold.
4. Generic templates. A downloaded ITP with the wrong standard, the wrong construction category, and someone else’s company name still in the footer. Yes, really.
5. Never issued, never briefed. The ITP gets approved by the client and the supervisor on the floor has never seen it.
6. Signed after the fact. Every hold point on a twelve week job signed on the same day, in the same pen. The ‘same pen’ test applies here first.

Signed at the hold points as the job ran. That’s what the ITP pages in a good MDR look like.
For asset owners: reviewing an ITP in ten minutes
You don’t need to be a welding engineer to review an ITP. Ten minutes with these questions will tell you most of what you need.
Is the construction category on it, and does it match the drawings? Are the acceptance criteria numbers, or “as per spec”? Do the hold points have a notice period and a named person? Is the order right, with NDT after cooling and before coating? Is there a line for repairs and re-testing? Does every line have a record? Is there a revision and an approval?
If more than two of those come back no, send it back before work starts. It’s a lot cheaper now than at final inspection.
For fabricators: the ITP is your best defence
If you run a good shop, a proper ITP is on your side.
It sets the scope of inspection before you price it, so nobody adds hold points halfway through and expects you to absorb the cost. It turns “the client wasn’t happy” into “hold point 7 was released on the 14th”. And when a weld gets questioned two years later, a signed IR and a signed hold point ends the conversation.
Write it for your floor, not for the tender. Brief your supervisor and your welders on it. Sign it as you go.
Free welding ITP template
We’ve put together two welding ITP templates, a detailed one for CC2 to CC4 and a one page version for smaller jobs, laid out in the order the work happens, with the columns above and the common structural steel line items already in. Both are Word downloads, no login, no email address.
- Detailed welding ITP template (Word), for CC2 to CC4 structural steel
- One page welding ITP template (Word), for smaller jobs
Use it as a starting point, not an answer. Change the lines to suit your job, your construction category and your client’s specification, and delete anything that doesn’t apply.
ITP FAQs
What does ITP stand for?
Inspection and test plan.
What is an ITP in construction?
A plan that lists every inspection and test activity for a package of work, in sequence, with the acceptance criteria, who does it, the hold and witness points, and the record that proves it was done.
What’s the difference between an ITP and an ITC?
The ITP is the plan. The ITC is the checklist used at one activity or batch.
What is a hold point?
A point the work can’t pass until the nominated person releases it in writing. A witness point only needs notice, so work can go ahead if nobody attends.
What’s the standard format for an ITP?
There’s no single mandated format. Most follow the same columns: activity, reference, acceptance criteria, method and extent, inspection point, responsibility, record and sign off, laid out in the order the work happens.
Who writes the ITP, and when is it due?
The fabricator typically writes it. The client or their representative reviews it, adds hold and witness points, and approves it before work starts. Transport for NSW asks for fabrication documents fifteen working days before work begins.
Competence, not paperwork
An ITP isn’t paperwork for its own sake. It’s the plan for checking the work while it can still be fixed. That only happens if someone competent writes it, follows it and signs it at the time. There is no point having a Rev 7 ITP still being approved when the project is going into the paint shop.
Technoweld reviews ITPs and WPS packages for asset owners and head contractors, and helps fabricators build ITPs their floor will actually use.